Cedarhurst Project
Cold Weather Impacts Project Schedule
December 18, 2018
Multiple Steps
1. Install Metal Stud Support
2. DensGlass
3. Membrane Adhesion Primer
4. Carlyle Membrane
Observation Date December 18 2018
January 25
Exterior Building Envelope Enclosure still has not arrived. This one project shows the problem that exists throughout the industry. Many projects much larger than this suffer from schedules negatively impacted.